Conference day two, Friday ready

  • Operator: Domagoj Ravlić (dravlic)
  • Date: 2026-10-08 UTC
  • Responding to: no handoff from the other lane since its 2026-10-01 handoff. Today is TOKEN2049 Singapore day two. My previous handoff: 2026-10-07.

BLUF

I kept conference day two clean like day one: no contact with the six validator hosts or the chain, and no StakeHub master commit. The objection window on the validator-5 reinstatement closes this evening UTC (plan). At 10:51Z no objection had arrived: origin/main carries only this lane's commits since the 2026-10-07 handoff, there is no new handoff from the other lane, neither repository has a PR comment since 2026-10-01, and the only PR updated since 2026-10-07 is #54, at its merge. Tomorrow, Friday 2026-10-09, is the release day of signer-rotation-20261007 if the window stays silent. The six operator instructions are checked against the deploy sheet and corrected, and a plain-language go-brief exists on my side. Small repository work today: the Z3 cycle inputs show the A666 route at epoch 11 (774a6025); the skeleton plan for the release after signer-rotation-20261007 is on main (335ee375); StakeHub PR #21 still merges cleanly, and its full test suite is running in the background.

Current state

  • Fleet and deployment boundary (Current State). No live probe today or yesterday. Last known state: 2026-10-06 09:13Z, all six at height 1115, READY WITH ATTENTION. Deployed: combined-fastpay-20260928 (1f8b332d…, source c93b2137). Repository: main at 335ee375 before this handoff; release/signer-rotation-20261007 at b4d3ebde (sheet dates corrected on 2026-10-06). Merged but undeployed: everything on main since c93b2137. Nothing on the hosts, the chain or StakeHub master changes before 2026-10-09. CI on main at the start of the day: all three workflows green on 51144786, bbe82032 and 54515003.
  • Z3 cycle inputs (774a6025). Row 2 now records the A666 route at epoch 11: policy 32c970e9…, valid heights 1110–10000, not paused, and the Ethereum pfUSDC source 2bae082a… as its only custody row. The sources hold only the prefix of the policy hash, so the full hash must come from a fresh read before the inputs are sealed. The epoch-10 value stays as the value before block 1110. The other "epoch 10" lines (:21, :95) concern the pfUSDC vault-bridge route and are correct. The lines that put A666 at NAV epoch 8 (:27, :69) are stale, because NAV epoch 9 was finalized at blocks 1108–1109. Updating them is a follow-up.
  • Next release skeleton (335ee375, plan, listed in the plans index below the current plan).
  • Already on main past the cut: 9d837bef (PR #54); 51144786 (account_tx fallback window and the archive-scan regression test); the docs-only commits e92b8157, 0a136eaa, f3f2a1e1, bbe82032, 54515003 and 774a6025. Since the cut, the only Rust changes are in tests, so the validator software is unchanged.
  • Candidates:
    • draft PR #47 (citadelculture, relative RPC child request spool path, issue #27; read path), which its owner must finish;
    • PR #52 (JJ2203-theRealOne, relative data directories), which waits for #47;
    • the citadelculture drafts #43–#46 (finality submit response check, node wrapper scripts, RPC probe across resolved addresses, monitor smoke with a sole proof warning; tooling), if their owner finishes them;
    • the Python fallback gaps (no atomic-swap rows; mis-numbered escrow, NFT and offer rows in blocks with swaps), owned by this lane;
    • the archive scan's "possibly incomplete" truncated flag, only if an exact flag is wanted;
    • the other lane's delayed-precommit fix, when it is pushed and reviewed; it changes consensus and needs its own qualification;
    • the testnet default of the RPC accept budget: the operator policy and postfiat-rpc.service.example still say 10000, while the release generator uses 100000;
    • FW-13 and FW-14 (StakeHub, the other lane's), tracked only.
  • Not before: signer-rotation-20261007 deployed and its activation done, CI green at the cut commit, and the full workspace suite run at the cut commit. Qualification and rollout follow the current plan, with rollback-one.sh going back to signer-rotation-20261007.
  • StakeHub PR #21 (wallet/readiness-and-route-check-20261005, head 9abec352).
  • git merge-tree against master 52eb686 reports no conflicts, and the merge can fast-forward (1 ahead, 0 behind).
  • The full suite (5,521 tests) runs in an isolated copy with its own environment (~/.cache/sh-pr21-20261008/, started 10:36:41Z). At 10:52Z it was still running at 61 percent, with 42 failures and 39 skips so far and no summary yet. Whether the failures match the known set of 84 environment-bound ones can be checked only when it ends.
  • The merge is planned for 2026-10-09, judged against the known failure set. The live StakeHub checkout is untouched.
  • Release-day preparation (my side, outside the repository).
  • I re-read the six operator instructions for 2026-10-09 against the deploy sheet and the release-day procedure and corrected two of them:
    • the store conversion now uses the sheet's order (validator-5, 0, 1, 2, 3, 4), its runuser command and its backup path (§7);
    • the activation step now names the sheet's 8.2 final-checkpoint votes and the FastPay commands, and keeps 8.5 for after the issuer's signature (§8).
  • A go-brief for the operator lists:
    • the go words in order: backup ok, rollout ok, store ok, relay ok (only if the other lane's agents are idle on the hosts), activate ok, fastpay ok;
    • the time each step takes and what can be undone;
    • the drop order if time runs short: relays first, then the two activation halves, never the after checks.
  • Task Node. No task today (documents and a test run only). The one network-proposed task for this account (the CorbanuTerminal Windows install-script fix) stays untouched. This handoff has no Task Node action.
  • CI on main (gh run list, read once at 10:50Z).
  • 774a6025: docs-build passed; product-security-ci and rust-ci running.
  • 335ee375: two push runs of each workflow; both docs-build runs passed; product-security-ci and rust-ci running.
  • Work server. 70 GB free. The suite's copy (under 1 GB) is deleted after the merge.
  • Devnet. Not touched. StakeHub master unchanged at 52eb686.

Next decision or action

My next steps, in order

On 2026-10-09. Each live step needs its own go on the day (deploy sheet).

  1. Go/no-go reads: no objection from the other lane; six-way agreement; CI green on the release tip; the other lane's agents idle on the hosts.
  2. Sections 1–4: the before state, the stage recheck, the fleet preflight, and the fresh signed canary backup from validator-1. Then the store conversion dry run on a copy of validator-1's store.
  3. Section 5: rollout one validator at a time (order: validator-1 canary, then 0, 2, 3, 4, 5), with one grant each. Section 6: the after checks.
  4. Section 7: the store conversion per host (validator-5, 0, 1, 2, 3, 4). The relay units only if the other lane's agents are idle (item p stays asked).
  5. Section 8: the bridge activation by validators 0–4, with the unsigned pftl_uniswap_route_bridge_policy_update handed to the other lane; the FastPay record signed by the six validators below height 10001. Then merge StakeHub PR #21 on the suite result, and update the records and the plan.

Only the other lane can provide

Each item shows the date first asked.

  • (a) The two NEAR Intents design questions (note). 2026-09-29.
  • (b) NAVCoin signer keys and custody rows (inputs). 2026-09-22.
  • (c) The Arc source row on the A666 route; epoch 11 has only the Ethereum source. 2026-09-28.
  • (d) A compatible governed NAV profile with fresh proofs for A666. 2026-09-22.
  • (e) StakeHub custody Q1. 2026-09-07.
  • (f) Reserve-proof successor adoption (PR #49). 2026-09-24.
  • (g)/(n) Validator-5: the objection window closes 2026-10-08 evening UTC; after the activation, one issuer signature for the bridge update. 2026-09-25 / 2026-10-01.
  • (h) The height-915 archive and the height-924 custodian. 2026-08-30.
  • (i) The AI-governance decision for Gate Zero Z2. 2026-09-03.
  • (j) The six inventory rows needing an operator decision (inventory). 2026-09-10.
  • (k) Disk items on the validators. 2026-09-28.
  • (l) The ETHEREUM_MAINNET_RPC_URL repository secret. 2026-09-28.
  • (m) The cap values. 2026-09-29.
  • (o) Permission to delete the other lane's old caches on the work server (~200 GB). 2026-10-01.
  • (p) A maintenance window for the relay units. 2026-10-01.
  • (q) FW-13 and FW-14. 2026-09-30.

References