Master State

Recorded: 2026-11-21; updated 2026-11-25. Status: the one source of truth for what the code is and what the network runs.

The rule

There is one line of code: main in this repository.

  • The six validators run code that is on main.
  • A release is built from a commit on main, and from nowhere else.
  • Work happens on a short-lived branch, goes into main by pull request, and the branch is deleted when it merges.
  • A branch that will not merge is tagged into the archive and deleted. It does not stay in the branch list.

2026-11-25: the running build is on main again

The validators run 04600868, the head of the release branch release/sol-exit-r2. It is main at e5c4f6ceb plus the release height (block 1890), a reviewer-installer fix and a rehearsal-test fix. From the rollout on 24 November until the merge it was not on main. It was merged into main on 25 November 2026 at 11:43 UTC as 26acd4639 (#234, which carries #228 and #230); git merge-base --is-ancestor 04600868 origin/main succeeds from that commit on, so the first rule above is met again.

What the validators run

Read from all six validators on 2026-11-25, 10:16–10:23 UTC, read-only status.

Fact Value
Chain postfiat-wan-devnet-2
Build revision 04600868 (release/sol-exit-r2; second Solana exit release, rules from block 1890)
On main Yes, since 26acd4639 (#234, 25 November 2026). Its base e5c4f6ceb is the merge of #223
Binary SHA-256 6dd2ee56d350854dc32f6542895fd51508d12901b068ac840be428d32f0f759b
Deployment manifest SHA-256 cd37a303d953e575727ee94141d2b897e0eff9c6cb9d91c5a09fd04b0ddb4d1b; deployment_manifest_verified true
Height 1897, all six agreeing on tip and state root

Releases since the join: sol-exit-r1 (71dbc9b3, rules from block 1841, 2026-11-23) and the second Solana exit release (04600868, rules from block 1890, 2026-11-24). Both were rolled one validator at a time (Current State).

21 November 2026, after the rollout

Read from all six validators on 2026-11-21 after the rollout.

Fact Value
Chain postfiat-wan-devnet-2
Source commit 674dbb18a29931d9ae749d28270e3c6cc508795a
main at the join 90c02da76
Code difference between the two None. They differ in seven documentation files only
Release name on the hosts main-r64-20261121
Binary SHA-256 95d5b237c991f57a9ea122e110f6a2d0c017bf9ca0a85315b2359ecba3b017d1
Signed manifest SHA-256 e4f2b8ff5781d4358f88c75c380f6c05ed121445f725d507d8c9383b5b388784
Height when the rollout finished 1738, all six agreeing on tip and state root

On 21 November the validators reported build revision 674dbb18. main reaches that commit through the merge 90c02da76, which adds documentation and changes no code.

How this state was reached

From 28 September to 21 November 2026 the validators ran releases cut from private release branches, while main moved separately. By 21 November the validators had 112 commits main lacked and main had about 1,360 commits the validators had never run.

On 21 November 2026 the two were joined:

  1. Build. The joined source (674dbb18a) was built into the binary above.
  2. Replay. On an offline copy of a live validator's data, the new binary verified the finalized checkpoint, re-verified all 1,734 blocks from genesis, and passed the full state verification. Tip and state root equalled those of all six live validators.
  3. Rollback check. The previous binary read the same data after the new one had used it, and again after the first upgraded validator had proposed a block.
  4. Rollout. One validator at a time, in the order 1, 0, 2, 3, 4, 5, from 19:58 to 20:19 UTC. After each host all six agreed on height, tip and state root. The previous binary, units and manifest stay installed on every host.
  5. Mixed-fleet tests. A test transaction was finalized with six accepted receipts at one new and five old (height 1735, proposed by the new version), at three and three (1736), with an old proposer and new voters (1737), and on the fully upgraded fleet (1738).
  6. Join. The joined source was merged into main (90c02da76).

The archive

Before any branch was deleted, every branch tip in the public repository and in the private repository was tagged in the private repository under archive/20261121/. There are 345 such tags, each verified to point at the identical commit. Nothing was discarded.

  • archive/20261121/public/<branch>: a branch that was in this repository.
  • archive/20261121/private/<branch>: a branch that was in the private repository.
  • archive/20261121/INDEX: the inventory. One row per branch with its category, what it holds, and the evidence for that call.

To bring a line of work back:

git fetch <private-remote> tag archive/20261121/private/<branch>
git switch -c <new-branch> archive/20261121/private/<branch>

Then open a pull request against main.

Of the 345 archived branches, 106 were already contained in main, 3 were superseded, 103 were backup snapshots, and 133 hold code or documents that are not in main (111 code, 22 documents only). The 111 code branches reduce to 64 distinct lines of work. Each needs a decision: merge it or leave it archived. The inventory lists them.

Where the bridges run

On 21 November 2026 every bridge service was moved to one checkout of main, at commit 7e67fc292, one at a time, each followed by a check.

2026-11-25: not all services run unmodified main

At the 25 November handoff (state of 24 November, 22:30 UTC) the relay host ran local edits, recorded on the branch ops/relay-host-live-edits-20261125 and in #229 (not merged) and #230 (on main since #234), and the Solana payout service ran a bundle of the second exit release plus a speed-up (c033278b). Moving them back to unmodified main is open work in that handoff.

Service Before Check after the move
Solana deposit relay, wallet API, health, re-anchor, prover tunnel A private branch A real 0.02 USDC deposit from Phantom was credited in 122 seconds, with no relay restart
Ethereum deposit bridge and wallet proxy A private branch from 13 November The route reports ready on the new process; a wallet request through the Task Node relay returns the chain height
Withdrawal (payout) and faucet A private branch from 16 November Both listen and answer; the payout service reports ready. No real withdrawal was sent on 21 November

The source for each deployed contract, Solana program and proof key is mapped in Bridge Audit Map.

Found during the move

  • Ethereum deposits had not been credited since 19 November. The bridge built its claims with a validator binary four releases old, and the chain rejected them, while the bridge kept reporting ready. Two deposits of 10 USDC each were waiting, one for two days. The bridge now uses the current binary; both were credited at heights 1741 to 1745 and confirmed on the validators.
  • The daily price-reading job was failing. It refused to run because the validator binary was not the one it pins. A B24 reading (epoch 9) was submitted at height 1842 on 23 November; none followed up to height 1897 (read-only read, 25 November). The job pins the sol-exit-r1 node binary while the fleet runs 04600868, so its runtime check will stop it until the pin moves (25 November handoff).
  • Not checked: a real Ethereum deposit and a real Ethereum withdrawal after the move; none is recorded up to 25 November. Real Solana withdrawals ran on 23 and 24 November (Current State).

B24 Schwab reading

Recorded 2026-11-23 from a live read of all six validators.

  • Fleet observed. All six ran sol-exit-r1: binary d46376ff131e941cd271632d79eb5cfe4a22269d31588bd24caddda962d3e39e, source 71dbc9b3, which is on main. This supersedes the table above for the binary. Its own record belongs to the Solana exit release.
  • Last reading. B24 epoch 9, NAV 1.006419, finalized at height 1844 (submit 1842, finalize 1843, pricing 1844, each accepted on all six).
  • Where the code is. The TEE Schwab reader moved from the navstrategies repository into tools/nav-reserve-proof/schwab-tee/, and the pipeline in ops/ uses only this repository (PR #220, not merged on 2026-11-23). Operating guide: B24 Schwab NAV Reading.
  • Still on the old path. Until PR #220 is merged and a new proof profile for the moved enclave is qualified, the 17:55 UTC timer captures from the navstrategies-now checkout.
  • Validator outboxes. Five validators had certified-send-outbox entries owned by root since 21 November 13:30, which blocked proposals through them. Ownership was corrected on 2026-11-23; the cause is not established.
  • Details: handoff 2026-11-23.

Keeping it true

Before a release, check that the commit being built is on main:

git merge-base --is-ancestor <commit> origin/main && echo on-main

After a release, compare every validator's build_git_revision with main, and update the table above. If they differ, that is an incident, not a state to leave.