Date: 2026-09-01

2026-11-25: historical inventory

The states below are those of 2026-09-01 and were not recomputed for this review. The generated Testnet Path shows D2 (public operator runbook) and D3 (topology thresholds) done since then. Current deployment facts are on Network Status.

Purpose: D1 of the testnet-path milestone — an inventory of every non-storage gate that must pass before a public testnet, so D2–D4 work against a fixed list. Scope boundary: storage gates (G0–G7) are tracked separately in the storage scaling milestone and are deliberately absent here.

This is an inventory, not policy. Every state below is read from a committed source; nothing is asserted beyond what those sources record. States: DONE (the committed source records the gate as satisfied), OPEN (the committed source records it as unsatisfied or still required), UNKNOWN (the true state is not recorded inside this repository).

Root-level and site-excluded evidence files are linked through the public repository because the docs site does not publish them.

Gate table

# Gate What it demands State Evidence Feeds
1 Security intake channel A private vulnerability-report channel is published and is the only intake path. DONE SECURITY.md § Reporting a Vulnerability D2, D4
2 Threat model A written threat model covers the adversaries a public testnet exposes. DONE SECURITY.md § Threat Model Summary; threat model D4
3 Validator key custody Production key custody (HSM/remote signer or encrypted keystore with rotation, separation, and audit logging) replaces plaintext software key files. OPEN SECURITY.md § Current Security Limitations; audit P1 custody closure requirement D2, D4
4 Public RPC hardening Public RPC runs only behind an authenticated TLS edge; the node rejects public and wildcard plaintext binds. DONE SECURITY.md § Current Security Limitations; public RPC operator policy D2
5 Owned-lane recovery evidence External deployment/operations evidence for the FastPay versioned ordered-recovery path. OPEN SECURITY.md § Current Security Limitations ("remains a real-value gate") D4
6 Release verification battery The full formatting/check/test/Clippy/docs/dependency/secret-scan battery passes on the exact release candidate. OPEN (per-release; no public-testnet candidate has run it) release process steps 1–2 D4
7 Release artifacts CycloneDX SBOM, signed deployment manifest, checksums, and a second-builder reproduction of the node hash. OPEN (per-release) release process step 3; signed deployment manifest runbook D4
8 Migration, rollback, canary Snapshot migration, rollback compatibility, and a rolling canary with explicit stop conditions are exercised for the release. OPEN (per-release) release process step 4 D4
9 Protected branch and required CI Branch protection and the eight named required jobs are enforced on main and cannot be bypassed. UNKNOWN (job definitions are committed; GitHub enforcement state is not recorded in this repository) release process § Protected-branch requirements; .github/workflows/ D4
10 Publication-candidate verification The secret-backed official-mainnet-fork job passes on the exact release revision, plus scripts/verify-publication-candidate and scripts/test-productionization-closure-table --require-closed. OPEN (per-release; scripts are committed) release process; scripts/verify-publication-candidate D4
11 AssetOrchard h_action external audit (P13) Independent review of the swap-circuit value-binding construction. OPEN audit scope ("independent review required before P13 can be closed") Z3, D4
12 Specialist consensus/circuit/bridge review Independent specialist review of consensus, circuits, contracts, and bridge code. OPEN audit § 12; release process production-promotion paragraph D4
13 SP1 guest/program reproduction SP1 guest/program reproduction and circuit review before proof-dependent activation. OPEN audit § 12 ("remain real-value activation gates") Z3, D4
14 Deployed privacy capture review Wire/browser/log capture review on the deployed system, beyond source scanning. OPEN audit § 12 ("remains a real-value evidence gate") Z3, D4
15 External bridge verifier deployment The federated settlement-release verifier is deployed at the external EVM boundary. OPEN audit § 12; mint settlement verifier Z3, D4
16 Public history hygiene Only sanitized history is public; the contaminated development history stays private. DONE audit § 12 ("Source publication is closed"); publication gate D4
17 Launch authority An explicit launch-authorization artifact exists (whitepaper: LaunchCertificate with ≥7 ratifiers). OPEN audit § 8 ("Exact artifact is not implemented") and § 12 ("launch authority") D4
18 Operations readiness Production alerting, independent fault drills, multi-region operations, and independent-operator evidence. OPEN operations readiness inventory § Result; audit § 12 D2, D3
19 Independent operator onboarding The public operator runbook exists. Independent completion requires the evidence below. OPEN Public-network prerequisites and an independent rehearsal are outstanding. D2
20 Topology/independence thresholds Placement preflight and concentration caps are defined for launch. OPEN thresholds proposed in launch-topology-thresholds.md (awaiting the operator's confirmation; placement preflight and L3 verifier not built); public launch boundary (mechanics may be green "before public operator diversity exists") D3
21 Privacy production burndown Production-grade privacy gates: external audits, live soak, anonymity-set and disclosure model, frozen upgrade/emergency procedures. OPEN privacy production burndown (production-grade goal list; PRIV rows Partial) Z3, D4

State count: 4 DONE, 16 OPEN, 1 UNKNOWN.

Per-release rows (6, 7, 8, 10) are process gates: the committed process defines them, and no committed receipt binds them to a public-testnet release candidate yet.

Top gaps

  1. Validator key custody (row 3) — plaintext software key files are the recorded posture; every public operator story (D2) inherits this until a production custody path exists.
  2. Independent onboarding (row 19). Close each open step with a release-specific record.
  3. Download and verify a signed release and a second builder's matching checksum.
  4. Obtain and verify public genesis, bootstrap peers and their published identities.
  5. Register an independent validator and retain its accepted registration receipt.
  6. Demonstrate production key custody and recovery with the chosen signer.
  7. Run the L1v2 sidecar and record a verified round on the public network.
  8. Exercise public monitoring and record a delivered alert.
  9. Run the documented upgrade and recovery on a public candidate and retain the independent operator's rehearsal report.
  10. Specialist external reviews (rows 11–14) — the longest-lead-time OPEN items; the P13 h_action scope is prepared but no independent review is recorded.
  11. Launch authority (row 17) — the whitepaper's LaunchCertificate artifact is explicitly not implemented, and no substitute authorization artifact is recorded.
  12. Protected-branch enforcement (row 9) — the only UNKNOWN: cheap to verify against GitHub settings, and the release process treats it as mandatory.