Corrected G4 Campaign: Executable Plan

Status: Completed — failed; no retry authorized Date: 2026-08-28 Baseline: main at 442c5a4d (vote-lock fix be4c7f44 + handoff) Predecessor plans: Vote-lock index fix (implemented, verified), Storage scaling milestone (governing gates) Motivating failures: G4 structural vote-path failure, Vote-lock fix handoff

BLUF for the executing agent

The vote-lock index fix is implemented and locally verified. The question this plan answers is the one that matters: does the chain now stay fast as it grows? The prior G4 campaign failed with height-5,000/height-50 p95 ratios of 2.808 (consensus round) and 2.762 (wallet-to-finality) against a required ≤1.10, with the entire material height relationship isolated to the two vote-lock stages that the fix bounds. Your job: freeze one corrected candidate binary (G1), refresh the binary-bound safety evidence (G2), extend the measurement runner to gate on the new vote-lock work counters, and run one new, unchanged 5+5+5 G4 measurement campaign under a fresh four-hour clock.

Pass → the storage milestone's local-qualification lane advances toward G5. Fail → diagnose once from the stage timing data, write the handoff, and stop. Either way, this plan ends with a definitive, evidence-bound answer. Do not loop, enlarge the matrix, or "retry" a failed gate.

Execution result — 2026-08-28

Outcome: FAILED; the one-run allowance is consumed. Do not resume, retry, relabel, or modify the frozen candidate under this plan.

The corrected vote-lock lookup worked on the selected path, but the chain still did not stay fast as history grew. All ten selected redb windows completed with exact literal receipts, six-validator convergence, zero reported full-history storage reads, and passing vote-lock work gates. Nevertheless, the height-5,000/height-50 p95 ratios were 2.693 for consensus round time and 2.649 for wallet-to-finality, both far above the 1.10 ceiling.

The first legacy control then failed the locked migration-position rule. Five validators each migrated once in finalized round 2 rather than round 1. That is a real campaign failure even though it appears to be a mismatch between the portable-snapshot control and the runner's first-round-only allowance. The runner stopped at 2026-08-28T22:33:12Z after 2,092.637 seconds. No legacy window completed, no final campaign report exists, and the qualification packet packager was not invoked.

Frozen identities

Item Corrected-run identity
Candidate source 442c5a4ddafed3aa0709f64e213fe0cedac5222d
Candidate binary SHA-256 29423cba098ce793ccab4a234ab26a2d30c6b11ad9eacd339b11b89cd6187c48
G1 candidate manifest SHA-256 b4a580f7f4c61db4992f83f823d6715cd712589eaaada9debde3f45622f1bf01
G2 safety manifest SHA-256 132220922f0d5b6e3728861f227e6aff4f28ad87f36fce6d78119f9e75ef78c7
Runner source 693855e3492bc3d37801653e90bc308969fbad85
Batch-builder binary SHA-256 754c9e8600f0a5c4f05e1fab62400ef222ae7ad154cecf533d8f5df4f69a1c0d
Corrected prepared-input manifest SHA-256 9d48530539eaf05a18879dbafb3d7c62862617c28b843ae300dc1d87ed05cb88
Campaign checkpoint SHA-256 847b60f924414825ac050fd901bc80b3dbb200d7db6d91c74f1357fc018cd6c1
Legacy failure receipt SHA-256 ce8703dfc16c22c3930508b314231c6992c82fa20c54bc9d9fa2254da9c98c38
Private diagnosis SHA-256 4c7bb67b8622de967b240a6583a34bd554e9a1c7f19672ef43a06f88ef7832f8

The private campaign directory is ~/repos/postfiat-storage-g4-measurement-693855e3-442c5a4d-v1. It contains validator private material and must never be committed, published, or deleted. The diagnosis is stored below it at diagnosis/corrected-g4-failure-diagnosis.json and contains only redaction-safe claims, but remains private under this plan.

Gate table

Required gate Evidence Result
Consensus p95 ratio ≤ 1.10 691.143 ms at height 50; 1,861.319 ms at height 5,000; ratio 2.693 FAIL
Wallet p95 ratio ≤ 1.10 706.998 ms at height 50; 1,872.667 ms at height 5,000; ratio 2.649 FAIL
No material positive height relationship The runner's listed-stage model says true, but omits the synchronous pre-setup outbox-resume phase carrying the observed cost FAIL — coverage gap
Selected/legacy height-50 comparison No legacy window completed NOT AVAILABLE / FAIL
Selected window correctness and bounded redb work All ten windows passed literal receipts, six-validator convergence, backend work, zero full-history reads, and resource gates PASS
Selected vote-lock bounded work All ten windows passed; all 50 allowed migrations occurred in round 1; 2,450 later vote operations examined at most 2 files and decoded at most 314 bytes PASS
Legacy vote-lock bounded work Five validators migrated once in finalized round 2; stable reason VOTE_LOCK_MIGRATION_AFTER_FIRST_FINALIZED_ROUND FAIL
Four-hour measurement budget Stopped after 2,092.637 of 14,400 seconds PASS on time; campaign incomplete
Overall candidate A candidate passes only if every gate passes FAIL

Single diagnosis and next owning surface

The remaining height cost is not in redb append and is no longer in vote-lock lookup. It occurs in the synchronous proposer phase before setup_start, which the runner does not time separately:

  1. transport_peer_certified_batch_round starts the round clock and calls resume_durable_certified_send_outbox before named setup timing (crates/node/src/transport_runtime.rs:2745-2774).
  2. Resume calls compact_completed_durable_certified_send_jobs (crates/node/src/transport_cli.rs:2466-2477).
  3. Compaction validates every retained completed certified-send tombstone and then pruning validates the same set again (transport_cli.rs:1848-1917,1962-2037).
  4. Each validation rereads job.json, batch.json, and certificate.json and rehashes both payloads (transport_cli.rs:2041-2126).

The frozen validator-0 outbox contains 240 completed tombstones/720 payload files at height 50 and the retention cap of 1,024 tombstones/3,072 payload files at height 5,000. In every selected window the slow proposer is validator 0 at rounds 4, 10, 16, 22, 28, 34, 40, and 46. Validator-0 consensus p95 rises from 745.581 ms to 1,922.521 ms, while the other non-migration proposers remain below 401 ms at height 5,000. This is a high-confidence source attribution, not a direct phase timer: the missing timing is itself part of the defect.

The next owner is therefore durable certified-send tombstone retention/resume in crates/node/src/transport_cli.rs, plus explicit phase coverage in crates/node/src/transport_runtime.rs. The work is proportional to retained history until the 1,024-tombstone cap and remains expensive at the cap. This plan does not authorize that fix or another campaign.

Prior identities (preserve as failed-campaign lineage; do not overwrite)

Item Value
Failed candidate source ae65844190f153cbdd49d1e5ac28ab96a19f7af4
Failed candidate binary SHA-256 891bfb42ea16af844fd72351ee38a90eaeb8f4302492a8fd64ce0f3db5dcbbf4
Runner source 1f478e0c473de42ecf43b4dd0925893de8f181ed (repo ~/repos/postfiat-storage-measurement-runner-1f478e0c)
Prior prepared-input manifest SHA-256 9ac31841a41ba514855a82f52650e1951ed97c9f99d54a4048a07407d6734c61
Prior campaign report SHA-256 88502bca7aaa4e576e5e9684b3d9b72d8c1b66e24b6c6c8e746f11807ac7eabb
Prior private run directory ~/repos/postfiat-storage-g4-measurement-1f478e0c-ae658441-v1 — contains validator private material; never commit, publish, or delete

Hard rules (from the active milestone — violating any invalidates the campaign)

  1. Build outside the clock. The four-hour budget covers measurement only. Freeze the binary and fleets first. Hitting the budget is a recorded TIME_BUDGET_EXCEEDED result, not permission to continue.
  2. Unchanged matrix. Five selected-redb windows at height 50, five at height 5,000, five legacy-JSONL control windows at height 50; 50 finalized rounds per window; six validators; exact signed inputs; literal receipts. Run selected-path windows before the expensive legacy controls.
  3. One clean candidate. Any change to node source or binary after the G1 freeze restarts G1–G4. Evidence-runner-only changes are permitted and are hash-bound separately.
  4. Diagnose once. A failed or timed-out gate gets one diagnosis from its own artifacts, a handoff, and a stop. No automatic restart, no larger matrix, no relabeled partial run.
  5. Offline only. No devnet contact, no deployment, no height-924 copy (G3 has its own authorization), no Task Node actions, no network mutation.
  6. Success per round means a valid certificate and matching literal accepted/rejected receipts and six-validator convergence on height, block hash, and state root — never elapsed time alone.

Step 0 — Host and repository preconditions

  1. Fix the build toolchain. ~/.local/bin/cc is a symlink directly to the zig binary, which rejects invocation as cc (error: unknown command: -m64). Fresh clean-checkout builds fail. Replace the cc symlink with a wrapper script that executes zig cc "$@" (and translate --target=x86_64-unknown-linux-gnu to --target=x86_64-linux-gnu, which this zig build requires), or install a real gcc. Add matching c++ and ar handling. Verify with a clean cargo build --release -p postfiat-node from a scratch checkout. Record the exact compiler identity in the build manifest — it is part of binary reproducibility.
  2. Push main. The G1 freeze must reference a commit that exists on origin/main. Pushing 442c5a4d requires operator authorization; obtain it before starting, or stop here and report. Do not commit the two unrelated untracked docs/security/ inventories.

Step 1 — G1: corrected candidate freeze

From a clean checkout of the pushed corrected commit:

  1. Build one release postfiat-node binary. Record: source commit, binary SHA-256, embedded build_git_revision, Rust toolchain, Cargo.lock SHA-256, build command, compiler/linker identity, host, and storage device — same schema as the prior G1 record in the milestone.
  2. Rerun the G1 regression set against that source: focused storage/node suites, the vote-lock suite (cargo test -p postfiat-node vote_lock), formatting, and warnings-denied Clippy.
  3. Update the milestone's G1 row: prior lineage preserved, corrected freeze recorded. The new binary must not change again until G4 completes.

Step 2 — G2: binary-bound safety refresh

The prior tamper/rollback receipts were bound to binary 891b…bf4 and are history, not evidence. Repeat every binary-bound G2 check against the corrected binary: tamper matrix, rollback, crash/restart atomicity, and storage-rebuild-transactional --verify-only fail-closed behavior. Reuse the existing G2 scripts and record fresh receipts. Design-level items that are not binary-bound do not need repetition; mark each reused item explicitly.

Step 3 — Runner extension: vote-lock bounded-work gate

In the runner repo (~/repos/postfiat-storage-measurement-runner-1f478e0c, worktree — do not touch candidate source):

  1. Parse the three new fields the fix added to postfiat.block_vote_creation_timing.v1 reports: vote_lock_files_examined, vote_lock_bytes_decoded, vote_lock_migration_performed (serde-defaulted; absent in legacy-control reports — treat absent as zero/false).
  2. Add a per-campaign gate, reported per window and per validator:
  3. vote_lock_migration_performed == true at most once per validator per window restore, and only in that window's first finalized round;
  4. for every other measured vote: vote_lock_files_examined <= 3 and vote_lock_bytes_decoded <= 4096;
  5. gate failure fails the window with a stable reason code.
  6. Add runner unit tests for the gate (bounded pass, migration-twice fail, late-migration fail, oversized-bytes fail, legacy report without fields).
  7. Commit in the runner repo and record the new runner source hash. Runner changes do not restart G1.

Why the migration allowance exists (do not "fix" it): the prepared fleets were written by the old binary. Their lock directories hold 49 (height 50) or 4,999 (height 5,000) lock files, all already at derived paths, and no index marker. The corrected binary's first vote per validator therefore runs the one-time verification migration — a single bounded-by-history scan — then writes the marker, and every later vote is O(1). This is designed behavior. One slow first round per window does not move a 50-round p95, and the counter gate proves the migration happened exactly once and never again. Do not regenerate or mutate the frozen fleets to pre-write markers; their content hashes are part of the preserved lineage.

Step 4 — New prepared-input manifest

Follow the merged prepared-input manifest workflow (90d68784 lineage) to produce one new manifest binding: corrected candidate source and binary hashes, updated runner source hash, the unchanged prepared height-50 and height-5,000 fleet digests and the height-50 legacy snapshot, the canonical batch-builder identity, corpus and certificate digests, topology, keys, timeouts, and instrumentation schema. Record the manifest SHA-256. This completes the open G1 "freeze topology/inputs" checklist item.

Step 5 — Run the campaign

  1. Create a fresh private run directory (~/repos/postfiat-storage-g4-measurement-<runner-rev>-<candidate-rev>-v1 naming convention). It will contain validator private material: never commit or publish it.
  2. Start the four-hour measurement clock only when measurement starts.
  3. Execute the unchanged matrix via the runner's campaign driver (run_campaign.py / run_paired_campaign.py per the runner README and the prior campaign's checkpoint workflow), selected windows first, with checkpoint/resume enabled and every window's fleet restored content-verified from the frozen digests.
  4. Package the final report and checkpoint with package_packet.py; record report and checkpoint SHA-256 values.

Execution note: item 4 was not applicable after the binding failure. The runner created no final report, and package_packet.py requires a complete, evidence-eligible campaign. Invoking it would not turn a partial failed run into a packet. The checkpoint, legacy failure receipt, and private diagnosis hashes above are the preserved failure evidence.

Step 6 — Pass/fail gates

The corrected candidate passes only if all of the following hold:

  • [ ] height-5,000 / height-50 p95 ratio ≤ 1.10 for consensus_round_ms;
  • [ ] height-5,000 / height-50 p95 ratio ≤ 1.10 for wallet_to_finality_ms;
  • [ ] no_positive_linear_height_relationship true — no synchronous stage shows a material positive height relationship;
  • [ ] selected/legacy height-50 comparison within the existing gate;
  • [ ] every window: literal receipts, six-validator convergence, bounded redb work counters, zero full-history storage reads (existing gates);
  • [ ] the new vote-lock bounded-work gate passes in every selected window at both heights;
  • [ ] the campaign finished inside the budget, or the result is recorded as TIME_BUDGET_EXCEEDED with only independently verifiable completed units preserved.

"Campaign completed" is never reported as "candidate passed." Report the gate booleans explicitly, as the prior handoff did.

Step 7 — Outcomes

On pass: - Update the milestone: corrected G4 result, all identities, gate table; local-qualification lane advances to assembling locally available G5 material. G3 remains blocked on its own authorization; deployment remains a separate decision. State plainly that this is an offline local result, not devnet or production evidence. - Write the handoff with all hashes, commands, gates, and omissions.

On fail: - Diagnose once, from the campaign's own stage timing reports: recompute the per-stage height regression (the prior campaign's method) and identify which stage now carries the material height relationship and whether the vote-lock counters stayed bounded (separating "fix didn't work" from "a third unbounded path exists"). - Write the handoff naming the implicated stage and the owning source file(s), update the milestone, and stop. Do not modify candidate source, rerun, or enlarge the matrix under this plan.

Explicit non-goals

  • No devnet access, deployment, or fleet mutation of any live system.
  • No height-924 validator-directory copy (G3 authorization is separate).
  • No candidate source changes after the G1 freeze — including "harmless" ones.
  • No reuse of prior binary-bound G2/G4 receipts as fresh evidence.
  • No publication of anything from private run directories.

Exit criteria

  • [x] Toolchain repaired and recorded; clean-checkout release build works.
  • [x] main pushed with operator authorization.
  • [x] G1 corrected freeze recorded (source, binary, toolchain, manifest).
  • [x] G2 binary-bound receipts refreshed against the corrected binary.
  • [x] Runner gate for vote-lock counters implemented, tested, hash-bound.
  • [x] One new prepared-input manifest recorded.
  • [x] One unchanged 5+5+5 campaign executed under one fresh four-hour clock.
  • [x] Gate table reported truthfully; milestone and handoff updated; on fail, a single evidence-bound diagnosis names the next owning surface.