Devnet Storage G6 Rehearsal Stop - 2026-08-30

  • Date: 2026-08-30 UTC
  • Classification: release-gate failure; no live-fleet incident
  • Status: stopped safely; candidate d0ae79f3 must not deploy

Later event: successor 10dd9f20 repaired the continuation defect and passed the old G6 runner, but a live canary exposed a different deployment topology failure and was rolled back. See the live-canary postmortem.

Executive summary

The planned transactional-storage rollout stopped at the mandatory G6 six-clone rehearsal. Candidate source d0ae79f3 successfully rebuilt and independently verified the storage of all six height-924 validators. The first certified continuation round, intended to produce height 925, then failed closed because the node tried to apply an older, superseded validator-registry update to the registry produced by a later update.

The exact rejection was:

live validator registry activation previous validator registry root mismatch

Validator-1 returned the same rejection for all three delivery attempts. None of the six working clones advanced beyond height 924.

This failure happened before any live deployment. No live binary, service, data directory, storage mode, validator registry, trust graph, or Cobalt authority state changed. A second authenticated fleet probe confirmed that all six live validators remained healthy and converged at height 924. Rollback was therefore unnecessary, and the Z1 observation clock never started.

What was being attempted

The rollout was intended to replace the controlled devnet's bounded JSON/JSONL storage with the qualified transactional redb candidate. The execution plan required the following sequence:

  1. Probe the live fleet without mutation.
  2. Copy six stopped validator directories and rehearse the exact migration.
  3. Deploy one validator at a time, retaining the old binary for rollback.
  4. Prove convergence, finality, transactional-backend use, and bounded reads.
  5. Prove that valid and invalid Cobalt registry transitions behave correctly.
  6. Publish receipts and begin the Z1 observation period.

Steps 2 and 3 were separate operator authorization points. Passing the offline performance gate did not authorize deployment, and passing the migration rebuild alone did not satisfy G6. G6 also required successful certified continuation against the real fleet history.

Pre-rehearsal fleet state

The read-only probe ran from 13:53:22Z through 13:53:39Z and found:

  • six reachable validators on postfiat-wan-devnet-2;
  • convergence at height 924 with one tip and one state root;
  • empty mempools;
  • identical deployed binary SHA-256 on all six hosts;
  • active validator, RPC, and advisory shadow services;
  • Cobalt authority mode 1 with identical registry and trust roots; and
  • no transactional generation or backend-mode record, as expected before the rollout.

The deployed fleet remained on binary d5e5ef630155e61b001b84edb404a4def7d29a9205f23d33d2ad9c37c2696caf. The proposed candidate binary was 9e82d9286d79307b6246a773882e744ade1abad6b10498c3ed2d9c9e6b78c80c, built from source d0ae79f3342fc78cbf907dbf231a60de8bc40606.

What passed in G6

Six distinct, stopped height-924 validator directories were authenticated before migration. The existing benchmarks/storage-scaling/run_migration_rehearsal.py workflow then:

  • rebuilt six transactional storage generations;
  • published each rebuilt generation;
  • ran six independent, non-mutating verify-only checks;
  • confirmed one shared migration packet root, 6a6b53eab81011ad469c23cb8088a4bc6d2b628d06a11c873f3adcb829c087e9389d6e32020361c965a0dd361e4807d5;
  • staged split validator keys for the isolated rehearsal; and
  • preserved convergence across the six source clones.

These results establish that the candidate could reconstruct and verify the height-924 state. They do not establish that it could safely continue the chain from that state.

Failure

The rehearsal began its first post-migration certified transparent round. The target block height was 925. Before storage activation or any later rollout phase, validator-1 rejected the proposed continuation three times with the same registry-root error.

The runner stopped. The failure receipt records:

  • operation: first post-migration certified transparent round at height 925;
  • phase: legacy finality;
  • reason code: VALIDATOR_REGISTRY_HISTORY_REAPPLICATION_ROOT_MISMATCH;
  • rejecting node: validator-1;
  • working-clone height after failure: 924 on all six; and
  • candidate disposition: DO_NOT_DEPLOY.

This is a fail-closed compatibility failure. It prevented an invalid continuation rather than accepting ambiguous registry history.

Technical diagnosis

The accepted chain history contains multiple validator-registry updates through height 924. The live registry at height 924 reflects the latest accepted update. During continuation, the candidate scans historical governance updates to determine which updates are due.

The bounded source diagnosis points to live_validator_registry_after_due_updates in crates/node/src/block_replay_wallet.rs. The function iterates the recorded updates and treats an update as already reflected only when applying its affected validator set to the current registry produces that update's new_registry_root.

That test is insufficient for superseded history:

  1. An earlier update is accepted and changes a validator key.
  2. A later update changes that key again.
  3. The persisted registry correctly reflects the later update.
  4. Reconstructing the earlier update's affected set from the current registry no longer equals the earlier update's new root.
  5. The earlier update is therefore treated as due again.
  6. Applying it to the later registry fails the required previous-root check.

The root check in apply_verified_validator_registry_update_to_registry_inner in crates/node/src/storage_commit.rs correctly rejects the operation because the current registry is not the earlier update's predecessor. The defect is therefore not that the check is too strict. The defect is the continuation logic attempting to reapply already-accepted, superseded history.

This is a bounded diagnosis, not a completed repair. The final cause should be considered proven only after an owning-boundary fix passes an exact regression and the affected qualification gates.

Impact

Live fleet

There was no live-fleet impact:

  • no deployment was attempted;
  • no service was restarted;
  • no live storage migration or activation occurred;
  • no governance action was submitted;
  • no validator or trust key changed;
  • no rollback was required; and
  • no Z1 observation period started.

The post-failure probe ran from 14:48:27Z through 14:48:45Z. It confirmed the original binary on all six validators, active services, empty mempools, no transactional backend, and unchanged height, tip, state root, registry root, and trust root.

Release and schedule

Candidate d0ae79f3 lost deployment eligibility. Its earlier G4 performance pass remains historical evidence for that exact binary, but it cannot override the G6 compatibility failure. Any repair creates a new source and binary identity and invalidates the affected qualification evidence.

Public-testnet progress remains blocked on a successor storage candidate.

Why the gate was effective

The rehearsal separated three claims that could otherwise be conflated:

  • Rebuild correctness: the candidate reconstructed all six stored states.
  • Verification correctness: independent read-only checks accepted those reconstructed states.
  • Continuation compatibility: the candidate could not extend the exact accepted chain history.

Synthetic and lower-height testing had not reproduced the sequence of superseding registry updates present in the real height-924 history. The six-clone gate caught that gap without putting the live fleet at risk. The correct operational result was to stop, not to weaken the root check or proceed because migration itself had passed.

Required remediation

A successor candidate must:

  1. Repair the owning validator-registry continuation boundary so accepted, superseded updates are not treated as due again.
  2. Preserve deterministic replay and the fail-closed previous-root and new-root checks.
  3. Add an exact regression with at least two accepted updates to the same validator record, beginning from the height-924-equivalent final registry and successfully producing the next certified height.
  4. Cover stale, reordered, duplicated, missing, and wrong-root update history, including rejection without durable mutation.
  5. Freeze a new source revision and binary hash.
  6. Repeat every qualification gate invalidated by the code change, including exact-history replay and the complete six-clone G6 workflow.
  7. Obtain a new written deployment decision after G6 passes.

No existing receipt authorizes modifying or deploying d0ae79f3.

Evidence

Redaction-safe, committed evidence:

Raw clones, signer material, logs, and the incomplete rehearsal are private operator artifacts. They must not be committed or published.